Keep and Share logo     Log In  |  Mobile View  |  Help  
 
Visiting
 
Select a Color
   
 
Jay & Trav's Basement: 2) Framing
 Light Table
 Film Strip
 List
 Slide Show
 Small Photos
 Medium Photos
 Large Photos

 

Jay & Trav's

Basement Project

Part 2: Framing

 

 

In this episode we look in on the progress of our favorite handyman as we switch from demolition and ducting to actual building!

We start with the delivery of our needed supplies.

The regular Bubba's at the Home Depot told me they would only deliver to our curbside, like in the street.  I was a bit upset. The next morning I spoke with the salesman at the Pro Desk and he fixed it.  Here are 42 pieces of mold resistant sheetrock where the delivery guy put them - inside the garage!

  

 Show Full Size   |     Download or Copy   |   Report as Objectionable 

 

He also pushed in our ten foot long bundle of lumber.

 

 Show Full Size   |     Download or Copy   |   Report as Objectionable 

 

Did I forget to mention that Sue came along as my handy helper? 

She stuck around for all of the following.

Here the delivery guy got our seven Laminated Veneer Lumber (LVL) beams to the top of the driveway.  Each was 1.75" by 14".  There were three twenty footers, two eighteens and two tens.  We used the rollycart to move them down to the garage.

 

 

 

 Show Full Size   |     Download or Copy   |   Report as Objectionable 

 

And here are the three twenty footers that will replace this wall.

 

 Show Full Size   |     Download or Copy   |   Report as Objectionable 

 

The others made it to the garage also.  Sue handled a rope tied to the front end of a beam while I did the same at the rear.  Then we just guided them down the driveway and into the house.

 

 Show Full Size   |     Download or Copy   |   Report as Objectionable 

 

We also got the rest of our order - except for the paint and moldings. The boys will have to pick the color first.

 

 Show Full Size   |     Download or Copy   |   Report as Objectionable 

 

We saved a bunch of wall insulation and plan on reusing it but keeping it out of the way is a pain.

 

 

 Show Full Size   |     Download or Copy   |   Report as Objectionable 

 

Our first project was the old hall wall.

 

 Show Full Size   |     Download or Copy   |   Report as Objectionable 

 

Even though I started 1" out from the top of the wall and the bottom 2x4s were directly under the upper boards, the vertical studs wouldn't clear the cement blocks in the middle of the wall.  Seems the wall bows in a bit. We had to rip a half inch off of three studs to get them to fit.

 

 Show Full Size   |     Download or Copy   |   Report as Objectionable 

 

Then it was on to installing the beams.

First we had to build a temporary wall to hold up the floor above.

 

 Show Full Size   |     Download or Copy   |   Report as Objectionable 

 

The big opening required two temporary walls, one on each side, because the floor joists didn't overlap enough.  So now we had three walls when we wanted none.

 

 Show Full Size   |     Download or Copy   |   Report as Objectionable 

 

After removing the old wall, we were down to two.

Then we built two stands to hold the beams up as we lifted them one at a time.  You can see one stand behind the step stool.

To get the beams up, I lifted one end while Sue took up the slack on a rope.  Tieing the rope off held one end steady while we repeated the process at the other end. 

 

 Show Full Size   |     Download or Copy   |   Report as Objectionable 

 

This worked really well and all three beams were soon sitting on the support boards.  Trav helped on the ropes this time around.

 

 

 Show Full Size   |     Download or Copy   |   Report as Objectionable 

 

Once on the support boards, the three beams needed to be nailed together into one five and a quarter inch thick beam.

It took three rows of 16d nails spaced a foot apart on each side per the manufacturer's instructions.  That's about 120 nails.

  

 Show Full Size   |     Download or Copy   |   Report as Objectionable 

 

I couldn't pound 120 three and a half inch nails into those rock solid beams so the boys paid for a palm nailer that works off of an air compressor.

It was loud, my wrist took a while to stop vibrating, but it got the job done.

 

 Show Full Size   |     Download or Copy   |   Report as Objectionable 

 

We moved the one now solid beam up tight to the floor joists with a hydraulic jack and then built the 2x6 supporting structure under each end, per our architect's specs.

 

 Show Full Size   |     Download or Copy   |   Report as Objectionable 

 

And with the temp walls gone we now have zero walls and a decent sized opening.

And the house didn't fall down.

Amazing.

 

 Show Full Size   |     Download or Copy   |   Report as Objectionable 

 

It looks good from either end.

It still feels strange walking through here without dodging a forest of 2x4s.

 

 Show Full Size   |     Download or Copy   |   Report as Objectionable 

 

Next it was on to do the same thing for the wall between the old hall and bedroom.  The only difference was that here we only needed one temporary wall.

 

 Show Full Size   |     Download or Copy   |   Report as Objectionable 

 

After taking down the old wall, we were left with a bunch of nails sticking down that had to be dealt with.

 

 Show Full Size   |     Download or Copy   |   Report as Objectionable 
 Copy this Photo
 Copy this Video
 Copy this Album

Creation date: Sep 21, 2010 5:00am     Last modified date: Dec 24, 2010 8:00am   Last visit date: Apr 9, 2025 9:40am
    Report Objectionable Content